OUR HISTORY
Kanga Potash has developed the project to pre-construction in just 6 years
2016
Development of a comprehensive geological model
Assessment of potential exploration drilling areas
DECEMBER
2016
Project initiation and drill site assessment
2017
FEBRUARY
2017
Mobilisation of drilling contractor
MAY
2017
Start of exploration drilling programme
AUGUST
2017
Exploration drilling programme successfully completed
Confirmation of geological and solution mining parameters
2018
OCTOBER
2018
Pre-Feasibility Study completed on a range of production scenarios
2019
SEPTEMBER
2019
Kick-off of DFS programme
2020
March
2020
Surface rights for plant, solution mining area and linear infrastructure corridor secured via decree
October
2020
DFS completed
2021
Two Letter of Intents from reputable trading companies for 100% of Kanga’s MOP production
March
2021
ESIA Letter of Conformity received
October
2021
Termsheet finalized for the supply of natural gas
Discussions with strategics, potential project finance parties and off-takers have commenced
December
2021
Submission of the application of the mining license and mining convention
2022
March
2022
Loango exploration permit extended (1st renewal)
MAY
2022
Gas Supply MOU signed
Negotiation process of the Kanga mining convention started
JUNE
2022
KP receives Kanga exploitation decree (gazetted in July 2022)